Shamrock Gardens Elementary School issued the following announcement on Aug. 23.
SCOPE OF WORK:
New 45-classroom replacement facility.
PROGRESS:
The Shamrock Gardens Elementary School construction manager completed the lime stabilization in the parking lots and loop roads. Curb and gutter installation began along with completing the storm and starting the fire and domestic water lines. CMU walls continued exterior and interior along with the MEP rough-ins in wall and below grade. Installation of structural steel continued and is expected to be complete in July.
CONSTRUCTION MANAGER /
GENERAL CONTRACTOR
Rodgers/Holt Brothers
ARCHITECT:
Little Diversified Architectural
LOCATION:
3301 Country Club Drive Charlotte, NC 28205
OVERALL BUDGET:
$35,358,351
PROJECT MANAGER:
Ken Brown
CONSTRUCTION PERCENT COMPLETE:
21%
OCCUPY ON:
August 2022
BOARD DISTRICT:
District 4
Original source can be found here.