Shamrock Gardens Construction Update 08/23/21

Construction

Shamrock Gardens Elementary School issued the following announcement on Aug. 23.

SCOPE OF WORK:

New 45-classroom replacement facility.

PROGRESS:

The Shamrock Gardens Elementary School construction manager completed the lime stabilization in the parking lots and loop roads. Curb and gutter installation began along with completing the storm and starting the fire and domestic water lines. CMU walls continued exterior and interior along with the MEP rough-ins in wall and below grade. Installation of structural steel continued and is expected to be complete in July.

CONSTRUCTION MANAGER /

GENERAL CONTRACTOR

Rodgers/Holt Brothers

ARCHITECT:

Little Diversified Architectural

LOCATION:

3301 Country Club Drive Charlotte, NC 28205

OVERALL BUDGET:

$35,358,351

PROJECT MANAGER:

Ken Brown

CONSTRUCTION PERCENT COMPLETE:

21%

OCCUPY ON:

August 2022

BOARD DISTRICT:

District 4

Original source can be found here.

ORGANIZATIONS IN THIS STORY

!RECEIVE ALERTS

The next time we write about any of these orgs, we’ll email you a link to the story. You may edit your settings or unsubscribe at any time.
Sign-up

DONATE

Help support the Metric Media Foundation's mission to restore community based news.
Donate

MORE NEWS